Colocation pricing comparison: how to compare quotes on one sheet

Updated November 2026

A fair colocation pricing comparison converts every quote to its total cost over the full term and its cost per kW per month, then scores everything else with weights you set before the bids arrive.

Headline rates hide most of the difference between bids. Escalators, one-time charges, free months, separately billed energy and cross-connect pricing decide which bid costs least over five years, and they rarely point the same way as the rate per kW.

On this page
  1. 1Set the method before you send the RFP
  2. 2Step 1: Screen out bids that miss a must-have
  3. 3Step 2: Normalize each colocation quote to term cost and cost per kW
  4. 4The Bid Normalizer
  5. 5Step 3: Score bids on weighted data center RFP evaluation criteria
  6. 6Red flags in colocation proposals
  7. 7Colocation proposal evaluation: from scores to a shortlist
  8. 8How to compare colocation quotes: FAQ
  9. 9Sources

1Set the method before you send the RFP

Write down your must-haves, your weights and your price formula before the first response arrives. Once you have seen a bid you like, it is hard not to pick weights that favor it. Put the weights in section 13 of your RFP so providers know how they will be judged. Our data center RFP template has a place for them.

2Step 1: Screen out bids that miss a must-have

A bid that fails any of these comes out before scoring. A high score elsewhere does not buy it back.

3Step 2: Normalize each colocation quote to term cost and cost per kW

Put every bid on the same footing: the same term, the same committed kW and the same quantities from your price sheet. Then work out two numbers.

Total term cost = one-time charges + every monthly charge over the term, with the annual increase applied each year + separately billed energy + any minimum-use charges, minus free months.

Cost per kW per month = total term cost ÷ (committed kW × months in the term).

The second number lets you compare a bid priced per kW with one priced per circuit or per cabinet. For per-circuit pricing, convert each circuit to usable kW first: at the common 80% loading under the National Electrical Code's continuous load rule, a 208 V, 30 A three-phase circuit carries about 8.6 kW and a 208 V, 30 A single-phase circuit about 5.0 kW.

Source: SlashGear, "What Is The 80% Rule For Circuit Breakers?", Jul 5 2026, on NEC 210.20(A). slashgear.com (circuit figures are our arithmetic.)

A worked example

Three hypothetical bids for the same requirement: 200 kW committed, 60-month term, six fiber cross-connects. These are made-up numbers to show the math, not market prices.

LineBid ABid BBid C
Headline rate$190 per kW, energy included$165 per kW, energy billed separately$178 per kW, energy included
Monthly space and power$38,000$33,000$35,600
Energy (provider's estimate)Included$9,000 a monthIncluded
Cross-connects6 at $3006 at $2506 at $450
Annual increase3%4%3%
Free monthsNone2None
One-time charges$25,000$10,000$90,000
Monthly total in month 60$44,795$49,360$43,107
Total over 60 months$2,560,643$2,726,358$2,530,079
Cost per kW per month$213.39$227.20$210.84
Rank by headline rate3rd1st2nd
Rank by total cost2nd3rd1st

Assumptions: the annual increase applies to space, power and cross-connects each year; separately billed energy is held flat; free months waive the space and power charge only.

Bid B has the lowest headline rate and the most expensive total. Its separately billed energy adds $540,000 over the term, more than the lower rate saves, and the extra 1% a year adds more on top. The two free months don't close the gap. Bid C carries the largest one-time charge and still costs least over the term.

4The Bid Normalizer

Enter up to three bids. The Normalizer works out total cost over the term and cost per kW per month, in your browser. Nothing you type is sent anywhere.

Input
Bid A
Bid B
Bid C
Bid name
Term in months
Committed kW
Monthly space and power charge ($)
Monthly cross-connects and other recurring charges ($)
Monthly energy billed separately, provider's estimate ($, 0 if included)
Annual increase (%)
Increase applies to cross-connects and other recurring charges
Free months
One-time charges ($)
Results
ResultBid ABid BBid C
Total term cost
Cost per kW per month
Month 1 invoice
Final month invoice
Rank by total (1 = lowest)
Price score (5 = lowest total)

These figures come from what you enter. They are not prices from us or from any provider.

5Step 3: Score bids on weighted data center RFP evaluation criteria

Price matters, but a bid that misses its delivery date or caps your density costs more than any rate difference. Score each criterion from 0 to 5, multiply by its weight and add up. These weights suit most retail and mid-size colocation requirements. Move them to suit yours before the RFP goes out.

CriterionWeightWhat earns a 5What earns a 1
Total cost over the term30Lowest total term costHighest, or prices missing
Power and cooling fit20Your highest density supported in the row, with room to growDensity met only with exceptions or at extra cost
Delivery date15Space and power ready before your date, with a remedy if missedDate not committed in writing
Network10Your carriers and on-ramps on-net, diverse entrancesKey carriers need a build
Contract terms10Capped increases, fair renewal, exit and relocation termsUncapped increases, market-rate renewal, provider may relocate you
Security and compliance10Current reports cover this building, every control you needLogos only, or the building is out of scope
Operations and support5Staffed at all hours, clear response targets, clean outage historyNo commitments in writing

Scoring price. Give the lowest total term cost a 5. Score every other bid as 5 × (lowest total ÷ that bid's total). In the example: Bid C scores 5.00, Bid A 4.94 and Bid B 4.64.

Example result

Criterion (weight)Bid ABid BBid C
Total cost (30)4.94 = 29.64.64 = 27.85.00 = 30.0
Power and cooling fit (20)4 = 16.05 = 20.03 = 12.0
Delivery date (15)5 = 15.03 = 9.03 = 9.0
Network (10)4 = 8.05 = 10.03 = 6.0
Contract terms (10)3 = 6.04 = 8.03 = 6.0
Security and compliance (10)4 = 8.04 = 8.05 = 10.0
Operations and support (5)4 = 4.03 = 3.04 = 4.0
Total (100)86.685.877.0

Weighted points = score ÷ 5 × weight. The cheapest bid finishes last. Bids A and B finish within one point of each other, which in practice is a tie: take both into negotiation and let the contract terms decide.

Download the scoring matrix (CSV)

6Red flags in colocation proposals

Sources: JLL, Aug 11 2026, jll.com. CBRE Research, Aug 27 2026, cbre.com

7Colocation proposal evaluation: from scores to a shortlist

  1. Send each provider your follow-up questions in writing, and have it confirm its answers in writing. In Cushman & Wakefield's own bid process, each vendor confirms its answers in writing before the client sees them.
  2. Take two finalists into negotiation, with a third in reserve if your timeline allows.
  3. Ask each finalist for its best final terms, using your price sheet again.
  4. Tell finalists where their terms fall short of what you need. Don't share another provider's prices.
  5. Re-run the Normalizer and the matrix on the final terms before you sign.

Morgan Lewis's review of colocation agreements covers the terms that decide most of the value: the power basis, delivery date remedies, service levels, escalators, renewal, liability caps and exit. Check that every one of them is settled in the final paper, not left for the order form.

Sources: Cushman & Wakefield, The Great Colocation Bake-Off, Jul 8 2022, cushmanwakefield.com. Morgan Lewis, Data Center Bytes, May 18 2026, morganlewis.com

Want us to run the RFP and compare the bids?

Send us the requirement. We reply by email within 24 hours, issue the RFP to providers you approve, put every response on one sheet and negotiate with you. Buyers pay nothing for placement: the provider you sign with pays us.

Send Us Your Requirement

Haven't scoped it yet? Start your scope with the planner.

8How to compare colocation quotes: FAQ

Should the lowest price win?

Only if it also passes every must-have and scores well on delivery and terms. Convert each bid to total cost over the term first, because the lowest headline rate is often not the lowest total.

How do we compare a bid priced per circuit with one priced per kW?

Convert each circuit to the kW you can use from it, then divide the total term cost by committed kW and months. At the common 80% loading, a 208 V, 30 A three-phase circuit carries about 8.6 kW.

How much weight should price get?

For most colocation requirements, 25% to 35% of the total score. Give it more when several bids meet every requirement with room to spare, and less when power, density or the delivery date is tight.

Should we tell providers how they scored?

Tell finalists which terms fall short, so they can improve them. Keep the full scores and other providers' prices to yourself.

What if two bids finish within a few points?

Treat it as a tie. Take both into negotiation and decide on the final contract terms and total cost.

Can you compare the responses for us?

Yes. Send us your requirement and we reply by email within 24 hours. We run the RFP, normalize every bid and compare them with you.